IS YOUR TIME RUNNING OUT???? MAKE SURE YOU DON’T MISS YOUR DEADLINE
Running Out of Time

FDEP requires you to submit a complete operating permit package 180 days prior to the expiration date of your existing permit.  These permit packages need to include the following:

1. Operations and Maintenance Performance Report*

2. Capacity Analysis Report*

3. Reuse Feasibility Report

4. Domestic Wastewater Operating Permit Applications Form 1 and Form 2A*

5. Current Sludge Hauler Agreement or Agricultural Use Plan

* Requires Certification by a Registered Engineering

For more information on how to start your WWTF Permit Renewal process contact us at info@excelengineers.com